The Innavik Hydro Project currently being built by the Pituvik Landholding Corporation in partnership with Innergex Renewable Energy Inc. will soon enable the Inuit community of Inukjuak to switch entirely to hydroelectric power. There will be a run-of-river power plant on the Innuksuac River.
The village is currently supplied by diesel-generated electricity. With the hydro project, it will be able to embark on an energy transition. The 7 megawatts of electricity generated by the plant will exceed the community’s needs, and Inukjuak will be able to use the surplus energy to support new local businesses and diversify its economy.
The dam, one of the first in the world to be built on permafrost, has been under construction for a year. It is a run-of-river dam, which means vast tracts of land won’t be flooded to create an artificial reservoir.
However, some land upstream will have to be submerged in order to funnel water to the plant. Contaminants including mercury and hydrocarbons could be released from the permafrost into the environment.